The walls are up and the City Hall construction continues to progress. Exterior and interior work completed throughout December includes:

  • Turn over south wing of building to start painting walls
  • Complete siding install
  • Sprinklers complete on main floor
  • Start T-Bar lighting in basement
  • Furnace HVAC work started
  • Gas lines being ran to furnace locations
  • Electrical switches/plugs install on main floor
  • Install lights on main floor where able