City Hall Progress Report: Sidewalk, Parking Lot Prep and Drywall

The City of Armstrong is dedicated to providing up-to-date information regarding the new City Hall building. As construction continues, the City will provide citizens with frequent updates.

The sounds of progress have been rippling through town as ANR Construction Ltd. crews completed preparations for sidewalks and parking lots. Interior work is still moving smoothly including:

  • waterproofing roof and sheathing
  • plumbers onsite
  • tree removal on Bridge St
  • framing full height of walls, main floor continued
  • drywall basement
  • parking lot and sidewalk preparations

To view current and past progress reports, visit the city hall webpage.

The City of Armstrong municipal office will be closed for the Christmas holiday Monday, December 26, 2022 to Monday January 2, 2023. Regular office hours will resume on Tuesday, January 3, 2023. Regular office hours are 8:30 a.m. to 4:30 p.m. Call 250-546-3023 or email info@cityofarmstrong.bc.ca for further assistance.